Installation: After determining
your project requirements, color choice and scheduling, the installation
process is a simple four-step process. T.J. Janca Construction,
Inc. erects barricades and caution tape, as required, to prevent inadvertent
pedestrian traffic on the job site for approximately 24 hours. We mechanically mix
the California recycled tire rubber buffings with urethane resin to the
specified resin-to-rubber weight ratios on site. This compound is placed,
screeded, and hand-troweled to the required thickness (1 to 3).
We recommend allowing 18 hours for drying time. (Please note: Drying time
will vary depending upon thickness, temperature and humidity.) The wear surface of
Pro-Tect Turf is applied at 3/8 to 1/2 thickness,
per specification. The wear course is composed of colored EPDM granules
that are mechanically mixed with urethane resin to the specified formula.
The shock pad is primed, and the wear surface is applied and hand-troweled
to provide a uniform surface at the specified thickness. A special primer
is applied to all solid substrates and on wear surface edges, where splices
or color changes may occur. Please allow a drying time of 12 to 24 hours,
depending upon weather conditions. Upon completion of
work, T.J. Janca Construction, Inc. will remove all tools, equipment,
excess materials and debris from the site. The playground is then ready
for immediate use. |
|||||||||||||||||||||||||||||||||||||||||||||||||
|
|
|||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||